  • Manohar Lal Sharma, Vs. The Principal Secretary & Ors., Writ Petition (Crl.) No. 120 Of 2012, R.M. Lodha, Cji, Madan B. Lokur, J, & Kurian Joseph, Supreme Court Of India [Full PDF Judgment].

    Extract From The Judgment

    2. Being such a significant, valuable and important natural resource, the allocation of coal blocks for the period 1993 to 2010 is the subject matter of this group of writ petitions filed in the nature of Public Interest Litigation, principally one by Manohar Lal Sharma and the other by the Common Cause. The allocation of coal blocks made during the above period by the Central Government, according to petitioners, is illegal and unconstitutional inter alia on the following grounds: (a) Non-compliance of the mandatory legal procedure under the Mines and Minerals (Development and Regulation) Act, 1957 (for short, ‘1957 Act’). 3 (b) Breach of Section 3(3)(a)(iii) of the Coal Mines (Nationalisation) Act, 1973 (for short, ‘CMN Act’). (c) Violation of the principle of Trusteeship of natural resources by gifting away precious resources as largesse. (d) Arbitrariness, lack of transparency, lack of objectivity and non-application of mind; and (e) Allotment tainted with mala fides and corruption and made in favour of ineligible companies tainted with mala fides and corruption.

    5. Principally, two prayers have been made in these matters, first, for quashing the entire allocation of coal blocks made to private companies by the Central Government between 1993 and 2012 and second, a court monitored investigation by the Central Bureau of Investigation (CBI) and Enforcement Directorate (ED) or by a Special Investigation Team (SIT) into the entire 5 allocation of coal blocks by the Central Government made between the above period covering all aspects.  

    155. The allocation of coal blocks through Government dispensation route, however laudable the object may be, also is illegal since it is impermissible as per the scheme of the CMN Act. No State Government or public sector undertakings of the State Governments are eligible for mining coal for commercial use. Since allocation of coal is permissible only to those categories under Section 3(3) and (4), the joint venture arrangement with ineligible firms is also impermissible. Equally, there is also no question of any consortium / leader / association in allocation. Only an undertaking satisfying the eligibility criteria referred to in Section 3(3) of the CMN Act, viz., which has a unit engaged in the production of iron and steel and generation of power, washing of coal obtained from mine or production of cement, is entitled to the allocation in addition to Central Government, a Central Government company or a Central Government corporation.

    156. In this context, it is worthwhile to note that the 1957 Act has been amended introducing Section 11-A w.e.f. 13.02.2012. As per the said amendment, the grant of reconnaissance permit or prospecting licence or mining lease in respect of an area containing coal or lignite can be made only through selection through auction by competitive bidding even among the eligible entities under Section 3(3)(a)(iii), referred to above. However, Government 162 companies, Government corporations or companies or corporations, which have been awarded power projects on the basis of competitive bids for tariff (including Ultra Mega Power Projects) have been exempted of allocation in favour of them is not meant to be through the competitive bidding process. 157. As we have already found that the allocations made, both under the Screening Committee route and the Government dispensation route, are arbitrary and illegal, what should be the consequences, is the issue which remains to be tackled. We are of the view that, to this limited extent, the matter requires further hearing. 158. By way of footnote, it may be clarified and we do, that no challenge was laid before us in respect of blocks where competitive bidding was held for the lowest tariff for power for Ultra Mega Power Projects (UMPPs). As a matter of fact, Mr. Prashant Bhushan, learned counsel for Common Cause submitted that since allocation for UMPPs is in accord with the opinion given in Natural Resources Allocation Reference20 and the benefit of the coal block is passed on to the public, the said allocations may not be cancelled. However, he submitted that in some cases the Government has allowed diversion of coal from UMPP to other end uses i.e. for commercial exploitation. Having regard to this, it is 163 directed that the coal blocks allocated for UMPP would only be used for UMPP and no diversion of coal for commercial exploitation would be permitted.